These are basic units of measurement based on Standard Method of Measurement 2(SMM2). Below are "must-know" items units for a QS.
1. Excavation of topsoil = m2
2. Excavation of reduced level/pits/basements/pile caps/trenches for g.beam = m3
3. Excavation of trenches for pipes = m
4. Concrete = m3
5. Formwork = m2
6. Reinforcement = kg
7. Fabric Reinforcement = m2
8. Sand Blinding/Similar Fine Materials = m2
9. Lean Concrete/Concrete Blinding = m3
10. Brickworks/Blockworks = m2
11. Skirtings/Bonding Ties = m
12. Finishes/Roof Coverings = m2
13. Normal Glass = m2
14. Special Glass(<10mm thk at >4.00m2/>10mm thk/Laminated/Solar control/Acrylic/Polycarbonate) = no.
15. Pipes/Gutters = m
16. Composite Items(fabricated off-site eg:door/window/sanitary fittings)/Fittings = no.
I think it might be helpful for those "in-case" forgotten units of measurements & as a super-fast guide for u & me without flipping the SMM. :) -FC
nice bLog! its interesting. thank you for sharing.... commercial land 3d survey sydney
ReplyDeleteBy deciding to cooperate with specialists, you do not waste your time and money. If you are looking for a company that offers comprehensive surveying services for companies and individuals, I recommend that you check out the website where you will find the offer of the company KB Surveys - GPR survey .